1.0 OBJECTIVE:

      To lay down procedure for operation of axial flow fan units (supply and return).

2.0 SCOPE:

      This SOP shall be applicable for all axial flow fan units (supply and return).

3.0 RESPONSIBILITY:

      Technician / Engineer / Executive

4.0 ACCOUNTABILITY:

      Engineering Head

5.0 PROCEDURE: 

5.1 For starting axial flow fan units 

5.1.1 Keep the selector switch at "HAND" position on the feeder.
5.1.2 Ensure emergency switch on the feeder is released condition.
5.1.3 Start axial flow fan unit by pressing red "ON" push button on the feeder.

5.2 For stopping axial flow fan units

5.2.1 Stop the axial flow fan unit by turning the selector switch to center position.

6.0 ABBREVIATION:

6.1 SOP : Standard Operating Procedure