    SOP for Change Control

    Standard operating procedure for handling the change control in pharmaceutical manufacturing facility.

    1.0 OBJECTIVE

    To lay down a procedure to define the mechanism for the initiate, review and authorization of changes in all master documents, master system and their control.

    2.0 SCOPE

    This procedure applies to handle the change control at the manufacturing facility.

    3.0 RESPONSIBILITY

    3.1 Executive –Quality assurance - Prepare the SOP and follow-up the SOP accordingly
    3.2 Asst. manager –Quality assurance & Regulatory affairs -Provide the support to the implementation of SOP and maintained the records.

    4.0 ACCOUNTABILITY

    4.1 Technical - Director.

    5.0 PROCEDURE

    5.1 This procedure is applicable to, but is not necessarily limited to all authorized documents/procedure including Validation protocols, Master formula records, Batch manufacturing records, Standard Operating procedure, Finish product specification, Standard testing procedure, Raw material specification, Packaging material specification.
    5.2 Initial of change (s)
    5.2.1 No “authorized” document can be changes without being duly authorized in accordance with this procedure
    5.2.2 Each document change request must be initiated by completion of a change control form (CCF) as per Annexure –II.
    5.2.3 The Asst. manager of Quality assurance & Regulatory affairs has the responsibility for controlling and tracking the CCF.
    5.2.4 The user department shall initiate the changes required by filling and submitted CCF from along with supporting documents to QA department.
    5.2.5 Changes to be established must have sound/ scientific justification.
    5.2.6 The impact of any proposed change on the quality of the final product must be fully evaluated and documented.
    5.2.7 Quality assurance will assign a CCF No. for the documentation.
    5.2.8 CCF numbering system: It contains combination of 8 digit and letters.
    e.g. XYZ/CC-XXXX
    Where XYZ - stands for company initial
    CC - Change control
    XXXX – 1st X stands for last digit of current year & next 3X’s stands for serial No.
    XYZ/CC - 18001 will be CCF No. for 1st change control of the year 2018.
    5.3 Management review and approval
    5.3.1 Circulate the CCF together with supporting documentation, to the Head – Quality assurance & Regulatory affairs, R&D, Production, Quality control and Warehouse as appropriate for their review and comments. Cost/ Productivity improvements must be fully justified and counter signed by the Plant Head/ Technical Director.
    5.4 Review and authorized process
    5.4.1 Submit CCF documents to Quality assurance for review and authorization before implementation.
    5.4.2 The Head of Quality assurance & Regulatory affairs must assign a category of change to each CCF.
    5.4.3 Category ‘A’ - No regulatory impact.
    Category ‘B’ - Minor changes (Notification to the Regulatory authorities required)
    Category ‘C’ - Major change/s that (Approval from the Regulatory authorities is required before implementation.)
    5.4.4 The review and authorised of a change shall include a sign by Head of Quality assurance & Regulatory affairs, Engineering, Quality control, Production, Warehouse and Engineering.
    5.4.5 The Head of Quality assurance & Regulatory affairs must ensure that all information (e.g. dates of submission /approval) relating to notification to Regulatory authorities is promptly transmitted to the Departmental heads to authorized the change (if applicable) shall finally authorize all change control (s).
    5.4.6 A duly completed change control form as per Annexure- II shall be finally signed by QA dept.
    5.4.7 CCF No will have stamping “CONTROLLED COPY” in red colour on right corner on each page of front side.
    5.4.8 Schematic diagram of change control as per Annexure-I.
    5.4.9 Issuance and controlling record will be maintained in QA department as per Annexure-III.

    6.0 ABBREVIATIONS

    6.1 SOP - Standard Operating Procedure
    6.2 No. - Number
    6.3 NA - Not Applicable
    6.4 QA - Quality Assurance
    6.5 CCF - Change Control Form
    6.6 R&D - Research & Development
    6.7 RA - Regulatory Affairs

    ANNEXURE – I 
    (SCHEMATIC DIAGRAM OF CHANGE CONTROL)


    ANNEXURE – II
    CHANGE CONTROL FORM (CCF)

    PART- A (To be filled by initiating department)            CF No. ____________________

    1.0    Change is requested for but not limited to followings:
    1.1     Production Department
    1.2     Quality control Department
    1.3     Engineering Department
    1.4     Warehouse Department
    1.5     Human resource development Department
    1.6     QA Department

    2.0   Proposed Change:     __________________________________________________________________________________________________________________________________________________________________________

    3.0   Existing System:      __________________________________________________________________________________________________________________________________________________________________________

    4.0 Effective Document(s)

    4.1   To be amended: __________________________________________________________________________________________________________________________________________________________________________

    4.2   To be cancelled:                      ______________________________________________________________________________________________________________________________________________________

    5.0   Reason for the change:        ______________________________________________________________________________________________________________________________________________________________________
                 
    6.0    Proposed Name:                                                        Signature:                                Date:

    7.0     Department Head’s Name:                                        Signature:                                Date:


    PART – B
    (TO BE FILLED BY CONCERNED DEPARTMENTS)
    MANAGEMENT REVIEW

    8.0    Circulated to            :                                                             Date _____________________
    Production
    Warehouse
    Quality Control
    Engineering
    R&D

    9.0    Review of impact of CCF

    Comments
    Reviewed by







    10.0    Cost/Productivity approval (Applicable/ Not Applicable)
     ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

    Head works: ______________   Sign: ________________ Date: _______________





    PART - C
    (TO BE FILLED BY HEAD –QUALITY ASSURANCE & REGULATORY AFFAIRS)
    ASSESSMENT AND AUTHORISATION OF CCF

    11.0    Date of review:                            Feasibility of change:       (Yes)                    (No)

    12.0    Category of change ( refers point 6.4.3)

                12.1       Category   ‘A’
                12.1       Category   ‘B’
                12.1       Category   ‘C’

    13.0     Date of regulatory authority approval (applicable/Not applicable)   Date : ________

                Signature of Head - Quality Assurance & Regulatory Affairs___________________

    14.0            QA Approval:     

    15.0            Final approval and authorization

               
    Technical Director
    Signature
    Date

    16.0    Date of implementation of the amend documentation: _________________________

    17.0    Amended document distribution on: ______________________________________


    ANNEXURE – III
    (CHANGE CONTROL LOG BOOK)
             
    S.No.
    CC No.
    Issue Date of CCF
    Name of Originator
    Originating Department
    Title of Change
    Approved
    or Reject
    Effective Date of
    Change
    Verified
    by QA
    Sign. /
    Date
    Remark












    Get editable documentsView List

    3 comments: Post Yours! Read Comment Policy ▼

    1. Sir is it required to initiate change control for the very new SOP.

      ReplyDelete
      Replies
      1. Change control is required for any chance in existing document or system. It is not required for new document.

        Delete
    2. But if we are introducing any new document in the system that may have impact on the existing system then this can be assessed significantly through change control only.

      ReplyDelete

    Please don't spam. Comments having links would not be published.


    Popular Categories ๐Ÿท️

    QA SOPs QC SOPs Micro SOPs HVAC Production SOPs Stores SOPs Checklists Maintenance SOPs HPLC Sterile GLP Validation Protocols Water System GDP Regulatory Maintenance Calibration Warning Letters Education B.Pharmacy
    Online Courses Salary Calculator
    Follow on Whatsapp


    Certificate Courses ๐ŸŽ–️

    Pharmaceutical Courses

    Follow Pharmaguideline


    DOCUMENTS ๐Ÿ“‹

    PHARMACEUTICAL DOCUMENTS




    Editable Pharmaceutical Documents in MS-Word Format. Ready to use SOPs, Protocols, Master Plans, Manuals and more...

    View


    adsbypg


    GET APP FOR NEWS UPDATES


    Android App