    SOP for Operation of High Tension (HT) Panel

    Standard operating procedure to operate the high tension panel.

    1.0 OBJECTIVE

    To lay down the procedure for operation of high tension (H.T.) panel.

    2.0 SCOPE

    This SOP shall be applicable for H.T.

    3.0 RESPONSIBILITY

    Operator/ Officer

    4.0 ACCOUNTABILITY

    HOD Engineering

    5.0 PROCEDURE

    5.1 For Putting ON the Panel

    5.1.1 Ensure breaker in its position inside the panel.
    5.1.2 Ensure that “TRIP CIRCUIT HEALTHY” indication appears on the panel.
    5.1.3 Check incoming voltage between R-Y, Y-B & B-R on the voltmeter provided, it should be 10.5 to 11KV.
    5.1.4 Close the breaker by turning the rotary switch to “CLOSE” position.
    5.1.5 Ensure vacuum circuit breaker is in ON position.
    5.1.6 Following indication lamps will glow.
    i) BREAKER ON, ii) TRIP CIRCUIT HEALTHY, iii) SPRING CHARGED & iv) SERVICE POSITION.
    5.1.7 Close Vacuum Circuit Breaker of transformer 1 by turning rotary switch to CLOSE POSITION.
    5.1.8 Close Vacuum Circuit Breaker of Transformer-2 by turning rotary switch to CLOSE POSITION.

    5.2 For Putting OFF the Panel

    5.2.1 Trip the vacuum circuit breaker of transformer-1 by turning the rotary switch to “TRIP” position.
    5.2.2 Breaker will trip and transformer -1will be put OFF.
    5.2.3 Trip Incomer circuit breaker of the transformer -2 by turning the rotary switch to TRIP position.
    5.2.4 Breaker will trip and transformer-2 will be put OFF.
    5.2.5 Trip incomer vacuum circuit breaker by turning the rotary switch to trip position. Entire panel will OFF.

    5.3 For Drawing out the Breaker

    5.3.1 Trip the circuit breaker, which is to be drawn out.
    5.3.2 Open the front door.
    5.3.3 Remove the metallic plug of control wires from its socket.
    5.3.4 Unlock the break by shifting a pin on the right side adjacent to plug.
    5.3.5 Draw out the breaker trolley with the help of special key provided.

    5.4 For drawing in the breaker

    5.4.1 Push the breaker trolley inside as you have taken out.
    5.4.2 Lock the pin, which was used to unlock it.
    5.4.3 Put the metallic plug of control wires into its socket.
    5.4.4 Close the door of the breaker panel.
    5.4.5 Breaker is ready to be put on.
    Related: SOP for Operation and Maintenance of Low Tension (L.T.) Panels

    6.0 ABBREVIATION

    6.1 SOP: Standard Operating Procedure
    Get editable documentsView List

    No comments:

    Post a Comment

    Please don't spam. Comments having links would not be published.


    Popular Categories ๐Ÿท️

    QA SOPs QC SOPs Micro SOPs HVAC Production SOPs Stores SOPs Checklists Maintenance SOPs HPLC Sterile GLP Validation Protocols Water System GDP Regulatory Maintenance Calibration Warning Letters Education B.Pharmacy
    Online Courses Salary Calculator
    Follow on Whatsapp


    Certificate Courses ๐ŸŽ–️

    Pharmaceutical Courses

    Follow Pharmaguideline


    DOCUMENTS ๐Ÿ“‹

    PHARMACEUTICAL DOCUMENTS




    Editable Pharmaceutical Documents in MS-Word Format. Ready to use SOPs, Protocols, Master Plans, Manuals and more...

    View


    adsbypg


    GET APP FOR NEWS UPDATES


    Android App