    Procedure for Line Clearance Before Commencing any Manufacturing Operation

    Know the procedure for the line clearance checklist in different manufacturing departments before starting the manufacturing operation as per GMP.

    1.0 Line clearance prior to dispensing

    1.1 Check the dispensing area for the following:
    1.2 All materials from previous operations have been removed.
    1.3 Equipment and accessories from previous operations have been removed.
    1.4 Paperwork from previous operations has been removed.

    1.5 Status labels from previous operations have been removed.
    1.6 The reverse laminar flow booths and surrounding are clean and status is displayed.
    1.7 All the equipment and accessories required for dispensing are clean and labeled as such.



    2.0 Line clearance prior to sifting / granulation / blending / compression / capsule Filling/ tablet inspection/ tablet coating / capsule Inspection and polishing

    2.1 Check the areas for the following:
    2.2 All materials and residues from previous operations have been removed.
    2.3 Utensils and accessories from previous operations have been removed.
    2.4 Containers used for previous operations have been removed.
    2.5 Paperwork from previous operations has been removed.
    2.6 Status labels from previous operations have been removed.
    2.7 All equipment is clean and labeled as such.
    2.8 Areas are clean and status is displayed.

    3.0 Line clearance prior to overprinting

    3.1 Check the area for the following:
    3.2 All materials from previous operations have been removed.
    3.3 All stereos from previous operations have been removed.
    3.4 Paperwork from previous operations has been removed.
    Related: SOP for Line Clearance in Manufacturing Area

    4.0 Line clearance prior to primary and secondary packaging

    4.1 Check the area for the following:
    4.2 All materials and residues from previous operations have been removed.
    4.3 Containers used for previous operations have been removed
    4.4 Paperwork from previous operations has been removed.
    4.5 Status labels from previous operations have been removed.
    4.6 All stereos from previous operations have been removed.
    4.7 All equipment is clean and labeled as such.
    4.8 Areas are clean and status is displayed.

    No comments:

    Post a Comment

    Please don't spam. Comments having links would not be published.


    Popular Categories ๐Ÿท️

    QA SOPs QC SOPs Micro SOPs HVAC Production SOPs Stores SOPs Checklists Maintenance SOPs HPLC Sterile GLP Validation Protocols Water System GDP Regulatory Maintenance Calibration Warning Letters Education B.Pharmacy
    Online Courses Salary Calculator
    Follow on Whatsapp


    Certificate Courses ๐ŸŽ–️

    Pharmaceutical Courses

    Follow Pharmaguideline


    DOCUMENTS ๐Ÿ“‹

    PHARMACEUTICAL DOCUMENTS




    Editable Pharmaceutical Documents in MS-Word Format. Ready to use SOPs, Protocols, Master Plans, Manuals and more...

    View


    adsbypg


    GET APP FOR NEWS UPDATES


    Android App