    1.0 OBJECTIVE

    To lay down the procedure for operation of Cad mill.

    2.0 SCOPE

    This SOP shall be applicable for the Cad Mill in Granulation Area at Production department.

    3.0 RESPONSIBILITY

    3.1 Execution: Operator
    3.2 Checking: Production Pharmacist & Above

    4.0 ACCOUNTABILITY

    HOD-Production / Assigned Designee

    5.0 PROCEDURE

    5.1 Production person shall ensure the cleanliness of the machine & area and ‘CLEANED’ label on it.
    5.2 Before starting the operation production person get the line clearance from QA person and affix the status label with Product Name, batch Details to equipment & area.
    5.3 Check the integrity of screen before & after completion of operation & record the observation “Screen integrity check Log”.
    5.4 Insert the beater assembly knife forward / Impact forward, depending on the requirement and tighten by means of four wing nuts and set the required speed by changing the V-belt and close the belt cover then tight the two wing nuts.
    5.5 Insert the screen of the required size.
    5.6 Affix throat and secure by means of further four wing nuts.
    5.7 Place the feed tray in position & set the container below discharge point of cad mill. Container lined with poly bag. One end of poly bag attached with discharge point of cad mill and other ends inside container.
    5.8 Switch “ON” the mains and then press green button to start the cad mill.
    5.9 Start the mill and feed the material through feed tray slowly.
    5.10 Switch “OFF” the mains after completion of operation and remove the container, tighten the poly bags and affix status label (milled).
    5.11 Affix “To Be Cleaned” label on the Cad mill & fill “Equipment Log Book”.

    Note: The new screen is procured it will be inspected and given the new I.D.No. (Identification No.), and if screen is found torned, with holes or integrity is not ok in it or unsuitable in any respect for usage, then it is to be replaced immediately and record it in “Sieve/Screen Inward, issuance & Destruction Register”.

    6.0 ABBREVIATIONS

    6.1 SOP: Standard Operating Procedure
    6.2 QA: Quality Assurance
    Get editable documentsView List

    No comments:

    Post a Comment

    Please don't spam. Comments having links would not be published.


    Popular Categories ๐Ÿท️

    QA SOPs QC SOPs Micro SOPs HVAC Production SOPs Stores SOPs Checklists Maintenance SOPs HPLC Sterile GLP Validation Protocols Water System GDP Regulatory Maintenance Calibration Warning Letters Education B.Pharmacy Regulatory Updates
    Online Courses Salary Calculator
    Follow on Whatsapp


    Certificate Courses ๐ŸŽ–️

    Pharmaceutical Courses

    Follow Pharmaguideline


    DOCUMENTS ๐Ÿ“‹

    PHARMACEUTICAL DOCUMENTS




    Editable Pharmaceutical Documents in MS-Word Format. Ready to use SOPs, Protocols, Master Plans, Manuals and more...

    View


    adsbypg


    GET APP FOR NEWS UPDATES


    Android App