Procedure for Sampling in Process Validation

Learn the sampling procedure during the process validation for blender and finished product including sampling locations and sample quantity.
Sampling plays a major role in achieving the accurate results of analysis. Sampling plan and procedure must be defined in validation protocols and training should be provided to the concerned staff before the validation activity starts.

Octagonal BlendeSamples are representative of whole batch. So it should be homogenous and should be taken properly from appropriate locations. Blend samples should be handled and weigh carefully because segregation may occur during weighing and transpiration. Sample quantity should not be more than the required and whole mass of each sample should be used in analysis.

Sampling for Blend:
Blends are tested for their homogeneity. Homogeneity of the blend is critical for the quality of the final product. Sample should be taken from at least 10 locations in the blender. Sampling location should be selected according to the difficulty of the blending. Areas of poor blending must be covered in sampling. Corners and discharge point must have sampling location. Blender geometry should be taken in consideration during the sampling of blender. Following are the sampling locations for octagonal blander.
1st Sampling Set: A=Left-Top (Left Arm)
2nd Sampling Set: B=Back-Top, C=Back-Middle
3rd Sampling Set: D=Center-Top, E= Center-Middle Top, F= Center-Bottom, G=Discharge-Port
4th Sampling Set: H= Front-Top, I=Front-Bottom
5th Sampling Set: J= Right-Top (Right Arm)
Blend uniformity samples should be taken directly from the blender just before unloading the blend. If it is not possible to perform sampling from blender then sample may be taken from the container after unloading. Three samples should be taken from each sampling location.
Acceptance criteria for blend uniformity = RSD ≤ 5%.

Sampling for Finished Product: During the packing/filling sample should be taken at following intervals.
A) Beginning: Sample should be taken at the beginning of the packing/filling process. First manufactured units should be collected as sample.
B) Middle: During the whole process samples should be collected to prepare one sample representing whole process.
C) End: Very last produced units should be collected as sample.
Additionally if any critical event occurs during the packing/filling process which may affect the product quality e.g. any breakdown in packing/filling machine, sample should be taken when process starts after breakdown.
Ankur Choudhary is India's first professional pharmaceutical blogger, author and founder of Pharmaceutical Guidelines, a widely-read pharmaceutical blog since 2008. Sign-up for the free email updates for your daily dose of pharmaceutical tips.
Email: .moc.enilediugamrahp@ofni Need Help: Ask Question

1 Comment so far : Add yours...

Melissa C.Styer said...


Post a Comment